PMP: Integration Management : Perform integrated change control Output
Perform integrated change control Output |
Approved Change Requests |
Change Log |
Project Management Plan Updates |
Project Documents Updates |
What are the outputs of Perform Integrated Change Control in project integration management?
The outputs of Perform Integrated Change Control in project integration management
What is a change log?
During the project, there might be changes required due to business needs. The documents contains the log of the changes is called change log.
You are beginning a new project. When should you use the Perform Integrated Change Control process?
-
a) Throughout the entire project
-
b) Only when closing out the project
-
c) Only after the project is completely funded
-
d) Only after the project scope is clearly defined
Answer: Throughout the entire project
Question: The five basic groups are: |
A. Planning, recording, directing, monitoring, evaluating |
B. Initiating, planning, executing, controlling, closing |
C. Planning, executing, monitoring, redirecting, closing |
D. Planning, executing, directing, closing, delivering |
Answer: 2
|
Answer explanation:
Integration Management
|
Question: PMI defines a project subprocess as having an input, _____, and an output. |
A. resolution and action |
B. formatting and creation |
C. tools and techniques |
D. process integration |
Answer: 3
|
Answer explanation:
Integration Management
|
Question: The ?triple constraint? philosophy involves which project attributes? |
A. Time, Quality, and Contracts |
B. Scope, Cost, and Communication |
C. Time, Cost, and Quality |
D. Product, Price, and People |
Answer: 3
|
Answer explanation:
Integration Management
|
Question: Which is a characteristic of a project? |
A. Defined objective |
B. Specific duration |
C. Defined tasks |
D. All of the above |
Answer: 4
|
Answer explanation:
Integration Management
|
Question: Project measurement baselines and project plans differ in that: |
A. Baselines are used to control the project and plans are used to execute |
B. Baselines change frequently and plans change infrequently |
C. Baselines change infrequently and plans change frequently |
D. A and B |
Answer: 1
|
Answer explanation:
Integration Management
|
Question: The purpose of configuration management is to: |
A. Guarantee the technical specification is current |
B. Control change throughout the project |
C. Inform stakeholders of changes |
D. Generate Engineering Change Requests |
Answer: 2
|
Answer explanation:
Integration Management
|
Question: A clear definition of the users? needs is the direct basis of the: |
A. Work breakdown structure |
B. Functional requirements |
C. Project cost estimates |
D. Termination decision |
Answer: 2
|
Answer explanation:
Integration Management
|
Question: When an organization chooses a project selection model, the most important criteria is: |
A. Flexibility |
B. Capability |
C. Realism |
D. Ease of use |
Answer: 3
|
Answer explanation:
Integration Management
|
Question: The principle objective of project stakeholder management is to: |
A. Identify all potential users of the project to ensure complete requirements analysis |
B. Thwart criticism of the project by developing a list of responses to known shareholder concerns |
C. Be proactive in curtailing stakeholder activities that might adversely affect the project |
D. Discredit negative stakeholders so that their arguments and concerns will not have much credence |
Answer: 3
|
Answer explanation:
Integration Management
|