PMP: Integration Management : Direct and Manage the project work Tools n Technique
Direct and Manage the project work Tools n Technique |
Expert Judgment |
Project Management Information System |
Meetings |
What are the several tools n techniques used to direct and manage the project
The several tools n techniques used to direct and manage the project:
Who can be the attendee of the meeting to manage the project
The attendee of the meeting to manage the project:
What is the main intention for the meeting?
The main intention for the meeting:
What can be PMIS software system will be tool to your project
PMIS software system will be tool to your project:
-
Work breakdown structure creation tools
-
Calendaring features
-
Scheduling abilities
-
Work authorization tools
-
Earned value management controls
-
Quality control charts, program evaluation and review technique (PERT) charts, Gantt charts, and other charting features
-
Calculations for the critical path, EVM, target dates based on the project schedule, and more
-
Resource tracking and levelling
-
Reporting functionality
Question: In what phase are a projects scope and objectives determined? |
A. Conceptual |
B. Development |
C. Implementation |
D. Close-out |
Answer: 1
|
Answer explanation:
Integration Management
|
Question: A project managers company operates in a high technology area requiring the integration and sharing of several functional specialties. The project manager is considering the appropriate organizational structure for a new project. The likely choice would be: |
A. Matrix |
B. Tight Matrix |
C. Functional |
D. Projectized |
Answer: 1
|
Answer explanation:
Integration Management
|
Question: The project schedule is useful in the generation of many important documents during the life span of the project. All of the following documents may be generated by the project schedule EXCEPT: |
A. Resource Utilization Histograms |
B. Cash Flow Forecasts |
C. Work Breakdown Structure |
D. Performance Measurement Baseline |
Answer: 3
|
Answer explanation:
Integration Management
|
Question: The project plan is used to: |
A. Finalize budget cost estimates |
B. Facilitate communication among stakeholders |
C. Provide a variable measurement process |
D. Develop corrective actions |
Answer: 2
|
Answer explanation:
Integration Management
|
Question: The risk management plan is a major component of the: |
A. Project plan |
B. Communications plan |
C. Procurement plan |
D. Contingency plan |
Answer: 1
|
Answer explanation:
Integration Management
|
Question: The change control process should include all of the following EXCEPT: |
A. Scope change control |
B. Resource leveling |
C. Contract administration |
D. Quality control |
Answer: 2
|
Answer explanation:
Integration Management
|