PMP: Integration Management : Close projct or phase Tools n Technique

Advertisements


Close projct or phase Tools n Technique
Analytical Techniques
Organizational Process Assets Updates
Meetings

Click here to Practice 3000+ PMP Question online from GICGAC.com: Covers PMBOK5, Covers Scope Management to Stakeholder Management: All 9 Management Area


What the Tools n Techniques is Close project or phase in project integration management?

The Tools n Techniques is Close project or phase in project integration management

  • Expert Judgment

  • Analytical Techniques

  • Meetings

Why the meeting will be conducted during the closure of the project?

The meeting will be conducted during the closure of the project

  • lessons learned

  • closeout

  • user group

  • Review meetings

What are the analytical techniques used during the closure of the project?

The analytical techniques used during the closure of the project:

  • Regression analysis

  • Trend analysis.



Question: The principle objective of project stakeholder management is to:
A. Identify all potential users of the project to ensure complete requirements analysis
B. Thwart criticism of the project by developing a list of responses to known shareholder concerns
C. Be proactive in curtailing stakeholder activities that might adversely affect the project
D. Discredit negative stakeholders so that their arguments and concerns will not have much credence
Answer: 3
Answer explanation:
Integration Management

Click here to Practice 3000+ PMP Question online from GICGAC.com: Covers PMBOK5, Covers Scope Management to Stakeholder Management: All 9 Management Area




Question: The decision process for project continuation or termination should not consider which of the following?
A. Sunk costs
B. Time to complete
C. Direct labor costs
D. Indirect costs
Answer: 1
Answer explanation:
Integration Management




Question: In what phase are a projects scope and objectives determined?
A. Conceptual
B. Development
C. Implementation
D. Close-out
Answer: 1
Answer explanation:
Integration Management




Question: A project managers company operates in a high technology area requiring the integration and sharing of several functional specialties. The project manager is considering the appropriate organizational structure for a new project. The likely choice would be:
A. Matrix
B. Tight Matrix
C. Functional
D. Projectized
Answer: 1
Answer explanation:
Integration Management




Question: The project schedule is useful in the generation of many important documents during the life span of the project. All of the following documents may be generated by the project schedule EXCEPT:
A. Resource Utilization Histograms
B. Cash Flow Forecasts
C. Work Breakdown Structure
D. Performance Measurement Baseline
Answer: 3
Answer explanation:
Integration Management


Advertisements
Advertisements

Mail: Support@gicgac.com