PMP: Integration Management : Developing the project management plan Tools n Technique

Advertisements


Developing the project management plan Tools n Technique
Expert Judgement
Facilitation techniques


What are several types of experts you should identify to make judgment for developing the project charter?

Several types of experts who make judgment for developing the project charter defined as:

  • Different unit or departments within the organization

  • Consultants

  • Stakeholders, including customers or sponsors

  • Professional and technical associations

  • Industry groups

  • Subject matter experts (SME)

  • Project management office (PMO)

What is Facilitation Techniques?

Facilitation techniques are the several techniques used by the facilitator which should have comprehensive solicitation within project management processes and guide the development of the project charter.

What are several Facilitation Techniques?

The various Facilitation Techniques are define below as:

  • Brainstorming

  • Conflict Resolution

  • Problem Solving

  • Meeting Management



Question: In what phase are a projects scope and objectives determined?
A. Conceptual
B. Development
C. Implementation
D. Close-out
Answer: 1
Answer explanation:
Integration Management




Question: A project managers company operates in a high technology area requiring the integration and sharing of several functional specialties. The project manager is considering the appropriate organizational structure for a new project. The likely choice would be:
A. Matrix
B. Tight Matrix
C. Functional
D. Projectized
Answer: 1
Answer explanation:
Integration Management




Question: The project schedule is useful in the generation of many important documents during the life span of the project. All of the following documents may be generated by the project schedule EXCEPT:
A. Resource Utilization Histograms
B. Cash Flow Forecasts
C. Work Breakdown Structure
D. Performance Measurement Baseline
Answer: 3
Answer explanation:
Integration Management




Question: The project plan is used to:
A. Finalize budget cost estimates
B. Facilitate communication among stakeholders
C. Provide a variable measurement process
D. Develop corrective actions
Answer: 2
Answer explanation:
Integration Management




Question: The risk management plan is a major component of the:
A. Project plan
B. Communications plan
C. Procurement plan
D. Contingency plan
Answer: 1
Answer explanation:
Integration Management




Question: The change control process should include all of the following EXCEPT:
A. Scope change control
B. Resource leveling
C. Contract administration
D. Quality control
Answer: 2
Answer explanation:
Integration Management