What are the output of direct and manage the project
The output of direct and manage the project
What are the work performance data includes?
The work performance information should be disseminated with monotonous collecting of data, including schedule progress, eventual delays and their causes, critical path activities, activities presenting delays, and actions for recovery and other important data for managing the work.
What are the project document will include?
The project document will include
-
Requirements documentation
-
-
Project logs (issues, assumptions, etc.)
-
Risk register
-
Stakeholder register
What do you mean by deliverable?
A deliverable is a verifiable result that can come in the form of a product or service.
Question: In what phase are a projects scope and objectives determined? |
A. Conceptual |
B. Development |
C. Implementation |
D. Close-out |
Answer: 1
|
Answer explanation:
Integration Management
|
Question: A project managers company operates in a high technology area requiring the integration and sharing of several functional specialties. The project manager is considering the appropriate organizational structure for a new project. The likely choice would be: |
A. Matrix |
B. Tight Matrix |
C. Functional |
D. Projectized |
Answer: 1
|
Answer explanation:
Integration Management
|
Question: The project schedule is useful in the generation of many important documents during the life span of the project. All of the following documents may be generated by the project schedule EXCEPT: |
A. Resource Utilization Histograms |
B. Cash Flow Forecasts |
C. Work Breakdown Structure |
D. Performance Measurement Baseline |
Answer: 3
|
Answer explanation:
Integration Management
|
Question: The project plan is used to: |
A. Finalize budget cost estimates |
B. Facilitate communication among stakeholders |
C. Provide a variable measurement process |
D. Develop corrective actions |
Answer: 2
|
Answer explanation:
Integration Management
|
Question: The risk management plan is a major component of the: |
A. Project plan |
B. Communications plan |
C. Procurement plan |
D. Contingency plan |
Answer: 1
|
Answer explanation:
Integration Management
|
Question: The change control process should include all of the following EXCEPT: |
A. Scope change control |
B. Resource leveling |
C. Contract administration |
D. Quality control |
Answer: 2
|
Answer explanation:
Integration Management
|