PMP: Integration Management : Direct and Manage the project work Input
Direct and Manage the project work Input |
Project Management Plan |
Approved Change Requests |
Enterprise Environmental Factors |
Organizational Process Assets |
What is the input of direct and manage the project work in project integration management?
The list of input of direct and manage the project work in project integration management
How the change to the project will be approved
The change control board (CCB) will review and approve the change before implementation.
The approved change request may be a corrective action, a preventative action, or a defect repair.
The approved change requests may modify the policies, project management plan, procedures, costs, or budgets or revise the schedules.
How the project management information system will be helpful to manage the project?
PMIS may contains automated tool like scheduling software tool, a configuration management system, an information collection and distribution system, or web interfaces to other online automated systems.
How the defect management database will be helpful to manage the project?
Issue and defect management database(s) containing previous issues and defect status, control information, issue and defect resolution, and action item results.
Question: In what phase are a projects scope and objectives determined? |
A. Conceptual |
B. Development |
C. Implementation |
D. Close-out |
Answer: 1
|
Answer explanation:
Integration Management
|
Question: A project managers company operates in a high technology area requiring the integration and sharing of several functional specialties. The project manager is considering the appropriate organizational structure for a new project. The likely choice would be: |
A. Matrix |
B. Tight Matrix |
C. Functional |
D. Projectized |
Answer: 1
|
Answer explanation:
Integration Management
|
Question: The project schedule is useful in the generation of many important documents during the life span of the project. All of the following documents may be generated by the project schedule EXCEPT: |
A. Resource Utilization Histograms |
B. Cash Flow Forecasts |
C. Work Breakdown Structure |
D. Performance Measurement Baseline |
Answer: 3
|
Answer explanation:
Integration Management
|
Question: The project plan is used to: |
A. Finalize budget cost estimates |
B. Facilitate communication among stakeholders |
C. Provide a variable measurement process |
D. Develop corrective actions |
Answer: 2
|
Answer explanation:
Integration Management
|
Question: The risk management plan is a major component of the: |
A. Project plan |
B. Communications plan |
C. Procurement plan |
D. Contingency plan |
Answer: 1
|
Answer explanation:
Integration Management
|
Question: The change control process should include all of the following EXCEPT: |
A. Scope change control |
B. Resource leveling |
C. Contract administration |
D. Quality control |
Answer: 2
|
Answer explanation:
Integration Management
|