PMP: Integration Management : Close projct or phase Output
Close projct or phase Output |
Final Product, Service, or Result Transition |
Organizational Process Assets Updates |
What the Output is Close project or phase in project integration management?
The Output is Close project or phase in project integration management
-
Final Product, Service, or Result Transition
-
Organizational Process Assets Updates
What are the assets need to be updated as organizational during the closure of the project?
The assets need to be updated as organizational during the closure of the project
What the key points Close project or phase in project integration management?
The key points Close project or phase in project integration management
-
According to the Organization standard, policy, guidelines, the project manager needs to close the project.
-
The project’s contract information needs to be visited during the closure of the project.
-
Best Practice, Lesson Learned document to be documents in Project document
-
Project documentation should be archived as part of project closure.
Question: The ?triple constraint? philosophy involves which project attributes? |
A. Time, Quality, and Contracts |
B. Scope, Cost, and Communication |
C. Time, Cost, and Quality |
D. Product, Price, and People |
Answer: 3
|
Answer explanation:
Integration Management
|
Question: Which is a characteristic of a project? |
A. Defined objective |
B. Specific duration |
C. Defined tasks |
D. All of the above |
Answer: 4
|
Answer explanation:
Integration Management
|
Question: Project measurement baselines and project plans differ in that: |
A. Baselines are used to control the project and plans are used to execute |
B. Baselines change frequently and plans change infrequently |
C. Baselines change infrequently and plans change frequently |
D. A and B |
Answer: 1
|
Answer explanation:
Integration Management
|
Question: The purpose of configuration management is to: |
A. Guarantee the technical specification is current |
B. Control change throughout the project |
C. Inform stakeholders of changes |
D. Generate Engineering Change Requests |
Answer: 2
|
Answer explanation:
Integration Management
|
Question: A clear definition of the users? needs is the direct basis of the: |
A. Work breakdown structure |
B. Functional requirements |
C. Project cost estimates |
D. Termination decision |
Answer: 2
|
Answer explanation:
Integration Management
|
Question: When an organization chooses a project selection model, the most important criteria is: |
A. Flexibility |
B. Capability |
C. Realism |
D. Ease of use |
Answer: 3
|
Answer explanation:
Integration Management
|