PMP: Integration Management : Close projct or phase Input

Advertisements


Close projct or phase Input
Project Management Plan
Accepted Deliverables
Organizational Process Assets

Click here to Practice 3000+ PMP Question online from GICGAC.com: Covers PMBOK5, Covers Scope Management to Stakeholder Management: All 9 Management Area


What the input is Close project or phase in project integration management?

The input is Close project or phase in project integration management

  • Project Management Plan

  • Accepted Deliverables

  • Organizational Process Assets

What are the deliverables will produce during the closure of the project

Product specification, Work performance document will be included in the accepted deliverables.

Partial or interim deliverables may also be included for phased or cancelled projects.

You are the project manager for your organization. When it comes to integrated change control, you must ensure that which one of the following is present?

  • a) Supporting detail for the change exists

  • b) Approval of the change from the project team

  • c) Approval of the change from an SME

  • d) Risk assessment for each proposed change

Answer: Supporting detail for the change exists

Baseline variances, a documented plan to management variances, and a proven methodology to offer corrective actions to the project plan are all part of which process?

  • a) Change management

  • b) The change control system

  • c) The scope change control

  • d) Integrated change control

Click here to Practice 3000+ PMP Question online from GICGAC.com: Covers PMBOK5, Covers Scope Management to Stakeholder Management: All 9 Management Area


Answer: Integrated change control

Integrated change control is a system to document changes, their impact, the response to those changes, and performance deficits.



Question: The five basic groups are:
A. Planning, recording, directing, monitoring, evaluating
B. Initiating, planning, executing, controlling, closing
C. Planning, executing, monitoring, redirecting, closing
D. Planning, executing, directing, closing, delivering
Answer: 2
Answer explanation:
Integration Management




Question: PMI defines a project subprocess as having an input, _____, and an output.
A. resolution and action
B. formatting and creation
C. tools and techniques
D. process integration
Answer: 3
Answer explanation:
Integration Management