PMP: Integration Management : Developing the project management plan Output
Developing the project management plan Output |
Project Management Plan |
What is the output of developing the project management plan in project integration management?
The output of developing the project management plan in project integration management:
What the project management plan highly contains in project integration management?
The Project management plan includes:
-
Project baseline
-
Project subsidiary plan
What the project baseline highly contains in project integration management?
The project baseline includes according to the project integration management:
-
Scope baseline
-
Schedule baseline
-
Cost baseline
What the project subsidiary plan highly contains in project integration management?
The project subsidiary plan highly contains in project integration management:
-
Scope management plan
-
Requirements management plan
-
Schedule management plan
-
Cost management plan
-
Quality management plan
-
Process improvement plan
-
Human resource management plan
-
Communications management plan
-
Risk management plan
-
Procurement management plan
-
Stakeholder management plan
Question: The ?triple constraint? philosophy involves which project attributes? |
A. Time, Quality, and Contracts |
B. Scope, Cost, and Communication |
C. Time, Cost, and Quality |
D. Product, Price, and People |
Answer: 3
|
Answer explanation:
Integration Management
|
Question: Which is a characteristic of a project? |
A. Defined objective |
B. Specific duration |
C. Defined tasks |
D. All of the above |
Answer: 4
|
Answer explanation:
Integration Management
|
Question: Project measurement baselines and project plans differ in that: |
A. Baselines are used to control the project and plans are used to execute |
B. Baselines change frequently and plans change infrequently |
C. Baselines change infrequently and plans change frequently |
D. A and B |
Answer: 1
|
Answer explanation:
Integration Management
|
Question: The purpose of configuration management is to: |
A. Guarantee the technical specification is current |
B. Control change throughout the project |
C. Inform stakeholders of changes |
D. Generate Engineering Change Requests |
Answer: 2
|
Answer explanation:
Integration Management
|
Question: A clear definition of the users? needs is the direct basis of the: |
A. Work breakdown structure |
B. Functional requirements |
C. Project cost estimates |
D. Termination decision |
Answer: 2
|
Answer explanation:
Integration Management
|
Question: When an organization chooses a project selection model, the most important criteria is: |
A. Flexibility |
B. Capability |
C. Realism |
D. Ease of use |
Answer: 3
|
Answer explanation:
Integration Management
|