                            | Question:	The practice of ceasing mass inspections and ending awards based on price is credited to:	 | 
                        
                        
                            | A.	 Edward Deming	 | 
                        
                        
                            | B.	 Philip Crosby	  | 
                        
                        
                            | C. 	 Juran	 | 
                        
                        
                            | D.	 Pareto	 | 
                        
                        
                            | 
                                Answer:	1	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	Scope planning is:	 | 
                        
                        
                            | A.	 Developing a comprehensive plan based on input from major stakeholders.	 | 
                        
                        
                            | B.	 Developing a written scope statement as the basis for future project decisions.	  | 
                        
                        
                            | C. 	 The process, which provides information for planning project milestones.	 | 
                        
                        
                            | D.	 Subdividing the project into smaller, more manageable components.	 | 
                        
                        
                            | 
                                Answer:	2	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	Completion of the _____________ scope is measured against the plan.	 | 
                        
                        
                            | A.	 Project	 | 
                        
                        
                            | B.	 Technical	  | 
                        
                        
                            | C. 	 Product	 | 
                        
                        
                            | D.	 Baseline	 | 
                        
                        
                            | 
                                Answer:	1	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	Project initiation is all of the following except:	 | 
                        
                        
                            | A.	 A process of formally recognizing that a new project exists.	 | 
                        
                        
                            | B.	 A process of formally recognizing that an existing project should continue into its next phase.	  | 
                        
                        
                            | C. 	 It links the project to the ongoing work of the performing organization.	 | 
                        
                        
                            | D.	 Its inputs are product description, strategic plan, constraints, and assumptions	 | 
                        
                        
                            | 
                                Answer:	4	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	Decision models used in project initiation include:	 | 
                        
                        
                            | A.	 Comparative approaches and scoring models	 | 
                        
                        
                            | B.	 Koenig analysis	  | 
                        
                        
                            | C. 	 Sales projections	 | 
                        
                        
                            | D.	 Iterative risk sensitivity analysis	 | 
                        
                        
                            | 
                                Answer:	1	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	A work breakdown structure is a:	 | 
                        
                        
                            | A.	 Result of the scope planning process	 | 
                        
                        
                            | B.	 Deliverable oriented grouping of project elements that organizes and defines the total scope of the project	  | 
                        
                        
                            | C. 	 Structure that can be used to track the project's time, cost, and quality performance against a defined baseline	 | 
                        
                        
                            | D.	 Valuable communications tool, but cannot be used to establish the number of required networks for cost control.	 | 
                        
                        
                            | 
                                Answer:	2	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	The items at the lowest level of the WBS are called	 | 
                        
                        
                            | A.	 Code of accounts	 | 
                        
                        
                            | B.	 Subtasks	  | 
                        
                        
                            | C. 	 Work packages	 | 
                        
                        
                            | D.	 Nodes	 | 
                        
                        
                            | 
                                Answer:	3	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	All of the following statements about the project charter are correct except:	 | 
                        
                        
                            | A.	 It is often an internal legal document	 | 
                        
                        
                            | B.	 It identifies the project manager's authority and responsibility	  | 
                        
                        
                            | C. 	 It identifies management and/or customer approved scope of the project	 | 
                        
                        
                            | D.	 It usually does not identify cost and time estimates	 | 
                        
                        
                            | 
                                Answer:	4	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	Maintenance should:	 | 
                        
                        
                            | A.	 Be considered part of the project life cycle because it is part of the total life cycle costing needed to do benefit/cost analysis in scope planning	 | 
                        
                        
                            | B.	 Should be part of the work breakdown structure to give the total scope of the required activities and effort	  | 
                        
                        
                            | C. 	 Not be considered as a part of the project life cycle	 | 
                        
                        
                            | D.	 Be managed carefully because it is often a source of scope creep	 | 
                        
                        
                            | 
                                Answer:	3	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	Projects are typically authorized as a result of any of the following except	 | 
                        
                        
                            | A.	 Market demand	 | 
                        
                        
                            | B.	 Successful RFP bidding	  | 
                        
                        
                            | C. 	 Regulatory requirement	 | 
                        
                        
                            | D.	 Technological advance	 | 
                        
                        
                            | 
                                Answer:	2	
                             | 
                        
                        