Question: The practice of ceasing mass inspections and ending awards based on price is credited to: |
A. Edward Deming |
B. Philip Crosby |
C. Juran |
D. Pareto |
Answer: 1
|
Answer explanation:
Scope Management
|
Question: Scope planning is: |
A. Developing a comprehensive plan based on input from major stakeholders. |
B. Developing a written scope statement as the basis for future project decisions. |
C. The process, which provides information for planning project milestones. |
D. Subdividing the project into smaller, more manageable components. |
Answer: 2
|
Answer explanation:
Scope Management
|
Question: Completion of the _____________ scope is measured against the plan. |
A. Project |
B. Technical |
C. Product |
D. Baseline |
Answer: 1
|
Answer explanation:
Scope Management
|
Question: Project initiation is all of the following except: |
A. A process of formally recognizing that a new project exists. |
B. A process of formally recognizing that an existing project should continue into its next phase. |
C. It links the project to the ongoing work of the performing organization. |
D. Its inputs are product description, strategic plan, constraints, and assumptions |
Answer: 4
|
Answer explanation:
Scope Management
|
Question: Decision models used in project initiation include: |
A. Comparative approaches and scoring models |
B. Koenig analysis |
C. Sales projections |
D. Iterative risk sensitivity analysis |
Answer: 1
|
Answer explanation:
Scope Management
|
Question: A work breakdown structure is a: |
A. Result of the scope planning process |
B. Deliverable oriented grouping of project elements that organizes and defines the total scope of the project |
C. Structure that can be used to track the project's time, cost, and quality performance against a defined baseline |
D. Valuable communications tool, but cannot be used to establish the number of required networks for cost control. |
Answer: 2
|
Answer explanation:
Scope Management
|
Question: The items at the lowest level of the WBS are called |
A. Code of accounts |
B. Subtasks |
C. Work packages |
D. Nodes |
Answer: 3
|
Answer explanation:
Scope Management
|
Question: All of the following statements about the project charter are correct except: |
A. It is often an internal legal document |
B. It identifies the project manager's authority and responsibility |
C. It identifies management and/or customer approved scope of the project |
D. It usually does not identify cost and time estimates |
Answer: 4
|
Answer explanation:
Scope Management
|
Question: Maintenance should: |
A. Be considered part of the project life cycle because it is part of the total life cycle costing needed to do benefit/cost analysis in scope planning |
B. Should be part of the work breakdown structure to give the total scope of the required activities and effort |
C. Not be considered as a part of the project life cycle |
D. Be managed carefully because it is often a source of scope creep |
Answer: 3
|
Answer explanation:
Scope Management
|
Question: Projects are typically authorized as a result of any of the following except |
A. Market demand |
B. Successful RFP bidding |
C. Regulatory requirement |
D. Technological advance |
Answer: 2
|
Answer explanation:
Scope Management
|