PMP: Scope Management : Define Scope Input
                    
                   
                    
                    What are the inputs of Define Scope in project scope management?
                    The inputs of Define Scope in project scope management?
                    
                    
                    
                     
                    You are managing a global project that involves stakeholders in several international locations. You are likely to consult the WBS dictionary to find: 
                     
                        - 
                            
a) The language translation of technical terms used in the project.
                         
                        - 
                            
b) Detailed deliverable, activity, and scheduling information about each component in the WBS.
                         
                        - 
                            
c) Information relating the legal constraints of relevant international locations to the development of the WBS.
                         
                        - 
                            
d) Strengths, weaknesses, opportunities, and threats (SWOT) of key stakeholders and their impact on the WBS.
                         
                      
                    
                    Answer: Detailed deliverable, activity, and scheduling information about each component in the WBS.  
                                     
                    
                       
                    
                    
                    
                        
                            | Question:	hat is the FIRST step to take as you begin planning?	 | 
                        
                        
                            | A.	 Identify the risks.	 | 
                        
                        
                            | B.	 Plan the scope.	  | 
                        
                        
                            | C. 	 Establish a resource plan.	 | 
                        
                        
                            | D.	 Complete a cost and schedule estimate.	 | 
                        
                        
                            | 
                                Answer:	2	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                   
                    
                    
                        
                            | Question:	Effective stakeholder management includes all of the following project elements EXCEPT:	 | 
                        
                        
                            | A.	 Clear requirements definition.	 | 
                        
                        
                            | B.	 Scope change control.	  | 
                        
                        
                            | C. 	 Timely status information.	 | 
                        
                        
                            | D.	 Frequent cost reports.	 | 
                        
                        
                            | 
                                Answer:	4	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	A likely result of using "compromise" to resolve a two-party conflict is:	 | 
                        
                        
                            | A.	 Lose-lose.	 | 
                        
                        
                            | B.	 Win-lose.	  | 
                        
                        
                            | C. 	 Win-win.	 | 
                        
                        
                            | D.	 Lose-win.	 | 
                        
                        
                            | 
                                Answer:	1	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	As part of the quality audit, the scope statement is checked against the work results to ensure the conformance to the customer requirements. The results should be documented and used for:	 | 
                        
                        
                            | A.	 Estimating future projects.	 | 
                        
                        
                            | B.	 Changing the project scope.	  | 
                        
                        
                            | C. 	 Defining future project tasks.	 | 
                        
                        
                            | D.	 Validating the quality process.	 | 
                        
                        
                            | 
                                Answer:	3	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	A generally accepted method to confirm accuracy of task progress is through:	 | 
                        
                        
                            | A.	 Earned value.	 | 
                        
                        
                            | B.	 Probability vs. outcome.	  | 
                        
                        
                            | C. 	 Maximum ceiling.	 | 
                        
                        
                            | D.	 Work breakdown structure.	 | 
                        
                        
                            | 
                                Answer:	1	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	Which of the following techniques is used to control the project schedule?	 | 
                        
                        
                            | A.	 Pareto diagram	 | 
                        
                        
                            | B.	 Performance measurement	  | 
                        
                        
                            | C. 	 Parametric modeling	 | 
                        
                        
                            | D.	 Statistical sampling	 | 
                        
                        
                            | 
                                Answer:	2	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             |