PMP: Scope Management : Control Scope Output
Control Scope Output
List of Control Scope Output
-
Work Performance Information
-
Change Requests
-
Project Management Plan Updates
-
Project Documents Updates
-
Organizational Process Assets Updates
Project sponsors have the GREATEST influence on the scope, quality, time, and cost of the project during the:
-
a) Concept phase.
-
b) Development phase.
-
c) Execution phase.
-
d) Close-down phase.
Answer: Concept phase.
A scope statement is important because it:
-
a) Provides the basis for making future project decisions.
-
b) Provides a brief summary of the project.
-
c) Approves the project for the stakeholders.
-
d) Provides criteria for measuring project cost.
Answer: Provides the basis for making future project decisions.
Question: hat is the FIRST step to take as you begin planning? |
A. Identify the risks. |
B. Plan the scope. |
C. Establish a resource plan. |
D. Complete a cost and schedule estimate. |
Answer: 2
|
Answer explanation:
Scope Management
|
Question: Effective stakeholder management includes all of the following project elements EXCEPT: |
A. Clear requirements definition. |
B. Scope change control. |
C. Timely status information. |
D. Frequent cost reports. |
Answer: 4
|
Answer explanation:
Scope Management
|
Question: A likely result of using "compromise" to resolve a two-party conflict is: |
A. Lose-lose. |
B. Win-lose. |
C. Win-win. |
D. Lose-win. |
Answer: 1
|
Answer explanation:
Scope Management
|
Question: As part of the quality audit, the scope statement is checked against the work results to ensure the conformance to the customer requirements. The results should be documented and used for: |
A. Estimating future projects. |
B. Changing the project scope. |
C. Defining future project tasks. |
D. Validating the quality process. |
Answer: 3
|
Answer explanation:
Scope Management
|
Question: A generally accepted method to confirm accuracy of task progress is through: |
A. Earned value. |
B. Probability vs. outcome. |
C. Maximum ceiling. |
D. Work breakdown structure. |
Answer: 1
|
Answer explanation:
Scope Management
|
Question: Which of the following techniques is used to control the project schedule? |
A. Pareto diagram |
B. Performance measurement |
C. Parametric modeling |
D. Statistical sampling |
Answer: 2
|
Answer explanation:
Scope Management
|