PMP: Scope Management : Create WBS Output

Advertisements

What are the Outputs of Create WBS in project scope management?

The Outputs of Create WBS in project scope management

  • Scope Baseline

  • Project Documents Updates



Question: hat is the FIRST step to take as you begin planning?
A. Identify the risks.
B. Plan the scope.
C. Establish a resource plan.
D. Complete a cost and schedule estimate.
Answer: 2
Answer explanation:
Scope Management




Question: Effective stakeholder management includes all of the following project elements EXCEPT:
A. Clear requirements definition.
B. Scope change control.
C. Timely status information.
D. Frequent cost reports.
Answer: 4
Answer explanation:
Scope Management




Question: A likely result of using "compromise" to resolve a two-party conflict is:
A. Lose-lose.
B. Win-lose.
C. Win-win.
D. Lose-win.
Answer: 1
Answer explanation:
Scope Management

Click here to Practice 3000+ PMP Question online from GICGAC.com: Covers PMBOK5, Covers Scope Management to Stakeholder Management: All 9 Management Area




Question: As part of the quality audit, the scope statement is checked against the work results to ensure the conformance to the customer requirements. The results should be documented and used for:
A. Estimating future projects.
B. Changing the project scope.
C. Defining future project tasks.
D. Validating the quality process.
Answer: 3
Answer explanation:
Scope Management




Question: A generally accepted method to confirm accuracy of task progress is through:
A. Earned value.
B. Probability vs. outcome.
C. Maximum ceiling.
D. Work breakdown structure.
Answer: 1
Answer explanation:
Scope Management




Question: Which of the following techniques is used to control the project schedule?
A. Pareto diagram
B. Performance measurement
C. Parametric modeling
D. Statistical sampling
Answer: 2
Answer explanation:
Scope Management