PMP: Scope Management : Collect Requirement Output
What are the Outputs of Collect Requirements in project scope management?
The Outputs of Collect Requirements in project scope management:
What the requirement document contains?
The requirement document contains
Question: Effective stakeholder management includes all of the following project elements EXCEPT: |
A. Clear requirements definition. |
B. Scope change control. |
C. Timely status information. |
D. Frequent cost reports. |
Answer: 4
|
Answer explanation:
Scope Management
|
Question: A likely result of using "compromise" to resolve a two-party conflict is: |
A. Lose-lose. |
B. Win-lose. |
C. Win-win. |
D. Lose-win. |
Answer: 1
|
Answer explanation:
Scope Management
|
Question: As part of the quality audit, the scope statement is checked against the work results to ensure the conformance to the customer requirements. The results should be documented and used for: |
A. Estimating future projects. |
B. Changing the project scope. |
C. Defining future project tasks. |
D. Validating the quality process. |
Answer: 3
|
Answer explanation:
Scope Management
|
Question: A generally accepted method to confirm accuracy of task progress is through: |
A. Earned value. |
B. Probability vs. outcome. |
C. Maximum ceiling. |
D. Work breakdown structure. |
Answer: 1
|
Answer explanation:
Scope Management
|
Question: Which of the following techniques is used to control the project schedule? |
A. Pareto diagram |
B. Performance measurement |
C. Parametric modeling |
D. Statistical sampling |
Answer: 2
|
Answer explanation:
Scope Management
|
Question: You are in charge of developing a new product for a bank. Your quality metrics are based on the 80th percentile of each of the last three products developed, This is an example of: |
A. Statistical sampling |
B. Metrics |
C. Benchmarking |
D. Operational definitions |
Answer: 3
|
Answer explanation:
Scope Management
|