PMP: Scope Management : Collect Requirement Output
                    
                    
                    What are the Outputs of Collect Requirements in project scope management?
                    The Outputs of Collect Requirements in project scope management:
                    
                    
                    
                    
                    
                    
                    What the requirement document contains?
                    The requirement document contains
                    
                    
                    
                  
                     
                    
                    
                    
                        
                            | Question:	Effective stakeholder management includes all of the following project elements EXCEPT:	 | 
                        
                        
                            | A.	 Clear requirements definition.	 | 
                        
                        
                            | B.	 Scope change control.	  | 
                        
                        
                            | C. 	 Timely status information.	 | 
                        
                        
                            | D.	 Frequent cost reports.	 | 
                        
                        
                            | 
                                Answer:	4	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	A likely result of using "compromise" to resolve a two-party conflict is:	 | 
                        
                        
                            | A.	 Lose-lose.	 | 
                        
                        
                            | B.	 Win-lose.	  | 
                        
                        
                            | C. 	 Win-win.	 | 
                        
                        
                            | D.	 Lose-win.	 | 
                        
                        
                            | 
                                Answer:	1	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	As part of the quality audit, the scope statement is checked against the work results to ensure the conformance to the customer requirements. The results should be documented and used for:	 | 
                        
                        
                            | A.	 Estimating future projects.	 | 
                        
                        
                            | B.	 Changing the project scope.	  | 
                        
                        
                            | C. 	 Defining future project tasks.	 | 
                        
                        
                            | D.	 Validating the quality process.	 | 
                        
                        
                            | 
                                Answer:	3	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	A generally accepted method to confirm accuracy of task progress is through:	 | 
                        
                        
                            | A.	 Earned value.	 | 
                        
                        
                            | B.	 Probability vs. outcome.	  | 
                        
                        
                            | C. 	 Maximum ceiling.	 | 
                        
                        
                            | D.	 Work breakdown structure.	 | 
                        
                        
                            | 
                                Answer:	1	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	Which of the following techniques is used to control the project schedule?	 | 
                        
                        
                            | A.	 Pareto diagram	 | 
                        
                        
                            | B.	 Performance measurement	  | 
                        
                        
                            | C. 	 Parametric modeling	 | 
                        
                        
                            | D.	 Statistical sampling	 | 
                        
                        
                            | 
                                Answer:	2	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             | 
                        
                    
                    
                    
                    
                    
                    
                    
                    
                        
                            | Question:	You are in charge of developing a new product for a bank. Your quality metrics are based on the 80th percentile of each of the last three products developed, This is an example of: 	 | 
                        
                        
                            | A.	 Statistical sampling 	 | 
                        
                        
                            | B.	 Metrics 	  | 
                        
                        
                            | C. 	 Benchmarking 	 | 
                        
                        
                            | D.	 Operational definitions	 | 
                        
                        
                            | 
                                Answer:	3	
                             | 
                        
                        
                            Answer explanation: 
                                Scope Management	
                             |