Estimate Costs Input



Estimate Costs Input
Cost Management Plan
Human Resource Management Plan
Scope Baseline
Project Schedule
Risk Register
Enterprise Environmental Factors
Organizational Process Assets


List of Estimate Costs Input

  • Cost Management Plan

  • Human Resource Management Plan

  • Scope Baseline

  • Project Schedule

  • Risk Register

  • Enterprise Environmental Factors

  • Organizational Process Assets

Which type of cost input defines that which kind of cost estimating templete to be use?

  • a) Project Schedule

  • b) Enterprise Environmental Factors

  • c) Organizational Process Assets

  • c) Scope Baseline

Answer: Organizational Process Assets

Which type of cost input defines that the reward and recognition to the project?

  • a) Human Resource Management Plan

  • b) Enterprise Environmental Factors

  • c) Organizational Process Assets

  • c) Scope Baseline

Answer: Human Resource Management Plan

Why the risk register will be used to estimate the cost?

  • a) The risk register should be reviewed to consider risk related to project

  • b) The risk register should be reviewed to consider risk response costs

  • c) The risk register should be reviewed to outsource the risk

  • c) None of the above

Answer: The risk register should be reviewed to consider risk response costs