PMP: Cost Management : Estimate Costs Input
Estimate Costs Input
Estimate Costs Input |
Cost Management Plan |
Human Resource Management Plan |
Scope Baseline |
Project Schedule |
Risk Register |
Enterprise Environmental Factors |
Organizational Process Assets |
List of Estimate Costs Input
-
Cost Management Plan
-
Human Resource Management Plan
-
Scope Baseline
-
Project Schedule
-
Risk Register
-
Enterprise Environmental Factors
-
Organizational Process Assets
Which type of cost input defines that which kind of cost estimating templete to be use?
Answer: Organizational Process Assets
Which type of cost input defines that the reward and recognition to the project?
-
a) Human Resource Management Plan
-
b) Enterprise Environmental Factors
-
c) Organizational Process Assets
-
c) Scope Baseline
Answer: Human Resource Management Plan
Why the risk register will be used to estimate the cost?
-
a) The risk register should be reviewed to consider risk related to project
-
b) The risk register should be reviewed to consider risk response costs
-
c) The risk register should be reviewed to outsource the risk
-
c) None of the above
Answer: The risk register should be reviewed to consider risk response costs