PMP: Cost Management : Control Costs Input

Control Costs Input



Control Costs Input
Project Management Plan
Project Funding Requirements
Work Performance Data
Organizational Process Assets

Click here to Practice 3000+ PMP Question online from GICGAC.com: Covers PMBOK5, Covers Scope Management to Stakeholder Management: All 9 Management Area


List of Control Costs Input

  • Project Management Plan

  • Project Funding Requirements

  • Work Performance Data

  • Organizational Process Assets

What is work performance data?

Work performance data will describe how each activity insde the project is progressing.

It also describes that which are deliverables are completed.

Work performance data also includes costs that is authorized and incurred.



Question: There are several communication methods used to share and distribute information to stakeholders, team members and management. Which of the following communication methods are used during execution phase to notify the public about environmental changes your project is going to cause after implementation?
A. Pull communication
B. Interactive communication
C. Informal communication
D. Push communication
Answer: 1
Answer explanation:
Communication Management




Question: A drug manufacturing project requires many pharmaceutical chemicals for synthesizing to produce an active ingredient or a drug. You are managing a contractor to supply all these chemicals in your drug manufacturing project. Recent quality testing of the drugs raised concerns over the quality of the materials supplied by the contractor. Which of the following must be done to make sure that all contractual obligations are followed by the contractor?
A. Escalate this issue to the sponsor and submit all drug testing reports
B. Reject all poor quality drugs and penalize the contractor
C. Convene a meeting with stakeholders and communicate the findings
D. Carryout audits and inspections to verify compliance in the seller's deliverables
Answer: 4
Answer explanation:
Communication Management




Question: A project manager is spending majority of his funding in the current phase of his project. Not only she is spending her money but also managing various resources in the project. What is the stakeholder influence on the project now compared to earlier phases?
A. Cannot be determined
B. More
C. Less
D. Same
Answer: 3
Answer explanation:
Communication Management




Question: A project manager is looking at various classification methods to share information among project stakeholders. Which of the following correctly classifies the different methods used?
A. Pull communication - Meetings Push communication - Newsletters Interactive communication - E- learning repository
B. Interactive communication -Meetings Push communication - E-learning repository Pull communication - Newsletters
C. Push communication - Meetings Pull communication - Newsletters Interactive communication - E- learning repository
D. Interactive communication -Meetings Push communication - Newsletters Pull communication - E-learning repository
Answer: 4
Answer explanation:
Communication Management

Click here to Practice 3000+ PMP Question online from GICGAC.com: Covers PMBOK5, Covers Scope Management to Stakeholder Management: All 9 Management Area


Sterling Silver White Round Diamond Heart Pendant (1/10 Cttw)



Question: Which of the following is not an appropriate method for dealing with a negative risk?
A. Avoid
B. Exploit
C. Transfer
D. Mitigate
Answer: 2
Answer explanation:
Communication Management



Mail: Support@gicgac.com