PMP: Cost Management : Control Costs Output
Control Costs Output
Control Costs Output |
Work Performance Information |
Budget Cost Forecasts |
Change Requests |
Project Management Plan Updates |
Project Documents Updates |
Organizational Process Assets Updates |
List of Control Costs Output
-
Work Performance Information
-
Budget Cost Forecasts
-
Change Requests
-
Project Management Plan Updates
-
Project Documents Updates
-
Organizational Process Assets Updates
At the end of the control cost, which document will update regaring causes of cost variances?
-
a) Project Management Plan
-
b) Project Document
-
c) Enterprise Environmental Factors
-
d) Organizational Process Assets
Answer: Organizational Process Assets