Control Costs Tools n Techniques



Control Costs Tools n Techniques
Earned Value Management
Forecasting
To Complete Performance Index (CPI)
Performance Reviews
Project Management Software
Reserve Analysis

Click here to Practice 3000+ PMP Question online from GICGAC.com: Covers PMBOK5, Covers Scope Management to Stakeholder Management: All 9 Management Area


List of Control Costs Tools n Techniques

  • Earned Value Management

  • Forecasting

  • To Complete Performance Index (CPI)

  • Performance Reviews

  • Project Management Software

  • Reserve Analysis

What is the formula for Schedule Variance (SV)?

  • a) EV - PV

  • b) EV − AC

  • c) EV/PV

  • d) EV/AC

Answer: EV - PV

What is the formula for Cost variance (CV)?

  • a) EV - PV

  • b) EV − AC

  • c) EV/PV

  • d) EV/AC

Answer: EV − AC

What is the formula for Schedule performance index (SPI)?

  • a) EV - PV

  • b) EV − AC

  • c) EV/PV

  • d) EV/AC

Answer: EV/PV