PMP: Cost Management : Determine Budget Output
Determine Budget Output
Determine Budget Output |
Cost Performance Baseline |
Project Funding Requirements |
Project Documents Updates |
List of Determine Budget Output
-
Cost Performance Baseline
-
Project Funding Requirements
-
Project Documents Updates
What are the various budget will include to baseline the cost?
-
Project expenditure
-
Management Reserve
-
Contigency Reserve
From which document you can derive the Total and Periodic funcding requirement?
-
a) Scope baseline
-
b) Schedule baseline
-
c) Cost baseline
-
d) Budget
Answer: Cost baseline