PMP: Time Management : Sequence Activities Tools n Technique
                    
                    Question: You are the project manager for Changing Tides video games. You have gathered the inputs for the Estimate Activity Durations process. Which of the following tools and techniques will you employ to produce the outputs for this process?
 A) Activity list, expert judgment, alternatives analysis, analogous estimating, parametric estimating, three-point estimating, and reserve analysis
 
B) Activity list, expert judgment, analogous estimating, parametric estimating, group decision-making techniques, and three-point estimating
 
C) Expert judgment, analogous estimating, parametric estimating, three-point estimating, group decision-making techniques, and reserve analysis
 
D) Expert judgment, alternatives analysis, analogous estimating, parametric estimating, three-point estimating, and group decision-making techniques
                    
Ans:Expert judgment, analogous estimating, parametric estimating, three-point estimating, group decision-making techniques, and reserve analysis
 
 
                   
                    
Sequence Activities Tools n Techniques
                    List of Sequence Activities Tools n Techniques
                    
                    
                    
                     
                    What are the list of relationships used in Precedence Diagramming Method? 
                    The list of relationships used in Precedence Diagramming Method
                   
                    
                        - 
                            
Finish-to-start (FS).  
                         
                        - 
                            
Finish-to-finish (FF).  
                         
                        - 
                            
Start-to-start (SS). 
                         
                          - 
                            
Start-to-finish (SF).