PMP: Time Management : Define Activities Tools n Technique

Advertisements

Define Activities Tools n Techniques

List of Define Activities Tools n Techniques

  • Decomposition

  • Rolling Wave Planning

  • Expert Judgment

Click here to Practice 3000+ PMP Question online from GICGAC.com: Covers PMBOK5, Covers Scope Management to Stakeholder Management: All 9 Management Area


What is Rolling Wave Planning?

Rolling wave planning is an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level.


Your developer has provided u with an estimate based on the cost per line of code .What type of estimate did the developer use to provide this information?


A. Parametric estimating.
B. Bottom-up- estimating.
C. Analogues estimating.
D. PERTestmating .