PMP: Communication Management : Control Communications Tools n Techniques
Control Communications Tools n Techniques
| Control Communications Tools n Techniques |
| Information management systems |
| Expert judgment |
| Meetings |
List of Control Communications Tools n Techniques
What is Information Management Systems?
An information management system provides a set of standard tools for the project manager to capture, store, and distribute information to stakeholders about the project’s costs, schedule progress, and performance.

| Question: Given multiple alternatives, the group decision method that allows the largest block in a group to decide (even if more than 50% of the members of the group do not support the decision) is called: |
| A. Commonality |
| B. Plurality |
| C. Unanimity |
| D. Majority |
|
Answer: 2
|
Answer explanation:
Communication Management
|
| Question: An important aspect of project management is the handling of stakeholder expectations. Typically, at what level are the stakeholders with respect to the project manager. |
| A. At higher levels and with greater authority |
| B. At all levels and with varying degrees of authority. |
| C. At higher levels but only the project sponsor has authority greater than the project manager. |
| D. At the same level with varying degrees of authority. |
|
Answer: 2
|
Answer explanation:
Communication Management
|
| Question: Effectiveness and efficiency are two important aspects of communication for a project manager. Identify which of the listed choices is incorrect. |
| A. Efficient communication means providing much more than the information needed |
| B. Effective communication means providing information at the right time |
| C. Efficient communication means providing only the information that is needed. |
| D. Effective communication means providing information in the right format. |
|
Answer: 1
|
Answer explanation:
Communication Management
|