Manage Project Team Output
Manage Project Team Output
Manage Project Team Output |
Change requests |
Project management plan updates |
Project documents updates |
Enterprise environmental factor updates |
Organizational process assets updates |
List of Manage Project Team Output
-
Change requests
-
Project management plan updates
-
Project documents updates
-
Enterprise environmental factor updates
-
Organizational process assets updates
Which document will update the Personnel skill after managing the project team?
-
a) Enterprise Environmental Factors
-
b) Project management plan
-
c) Project documents
-
d) Organizational process assets
Answer: Enterprise Environmental Factors
Which document will update the Roles description after managing the project team?
-
a) Enterprise Environmental Factors
-
b) Project management plan
-
c) Project documents
-
d) Organizational process assets
Answer: Organizational process assets