PMP: Risk Management : Identify Risks Input
                    
                   
                    Identify Risks Input
                    List of Identify Risks Input
                    
                    
                        - 
                            
Risk management plan
                         
                        - 
                            
Cost management plan
                         
                        - 
                            
Schedule management plan
                         
                        - 
                            
Quality management plan
                         
                        - 
                            
Human resource management plan
                         
                          - 
                            
Scope baseline
                         
                        - 
                            
Activity cost estimates
                         
                        - 
                            
Activity duration estimates
                         
                        - 
                            
Stakeholder register
                         
                        - 
                            
Project documents
                         
                         - 
                            
Procurement documents
                         
                        - 
                            
Enterprise environmental factors
                         
                         - 
                            
Organizational process assets
                         
                       
                    
                    
                     
                    Which is not considered as input to identify the risk?
                     
                    Answer: Project charter