Identify Risks Input

List of Identify Risks Input

  • Risk management plan

  • Cost management plan

  • Schedule management plan

  • Quality management plan

  • Human resource management plan

  • Scope baseline

  • Activity cost estimates

  • Activity duration estimates

  • Stakeholder register

  • Project documents

  • Procurement documents

  • Enterprise environmental factors

  • Organizational process assets

Which is not considered as input to identify the risk?

  • a) Risk Management Plan

  • b) Cost Management Plan

  • c) Schedule Management Plan

  • d) Project charter

Answer: Project charter