PMP: Stakeholder Management : Control Stakeholder Engagement Output

Advertisements

Control Stakeholder Engagement Output

List of Control Stakeholder Engagement Output

  • Work performance information

  • Change requests

  • Project management plan updates

  • Project documents updates

  • Organizational process assets updates

Click here to Practice 3000+ PMP Question online from GICGAC.com: Covers PMBOK5, Covers Scope Management to Stakeholder Management: All 9 Management Area


What are the key documents respect to Organizational asset will update after controlling the stakeholder engagement?

The key documents respect to Organizational asset will update after controlling the stakeholder engagement are:

  • Stakeholder notifications

  • Project reports

  • Project presentations

  • Project records

  • Feedback from stakeholders

Stuart is the project manager for a large construction project his company is completing for a client. This project has internal and external stakeholders, including members of the community who are opposed to the project, although it has been approved by the city. Harold is preparing to create a stakeholder management plan and he's gathering several inputs for the plan's creation. Which one of the following inputs will most help Harold create a strategy for stakeholder management and engagement?

  • a) Project management plan

  • b) Stakeholder register

  • c) Enterprise environmental factors

  • d) Communications management plan

Answer: Stakeholder register