Practice Free Communication Management Set 5 Questions Set 1
|
|
|
|
|
A change request has just been formally documented and approved by the Change Control Board. The project manager now needs to communicate this to a project team member. Which of the following activities must the project manager necessarily do?
|
|
|
|
|
|
|