Learn and Practice Free Total PMP Set 9 questions

Click below to Practice Free Total PMP Set 9 Questions


You can get answer of the below sample questions by going through the above Question sets.


Which method allows for loops or conditional branches?


Option 1: PERT
Option 2: PDM
Option 3: GERT
Option 4: ADM
Option 5: CDM


Under what circumstances is it better for a contractor to subcontract?


Option 1: The subcontractor possesses special technical and engineering skills that the contractor does not have.
Option 2: The work to be subcontracted represents almost all of the overall work effort.
Option 3: The subcontractor can perform the work at a lower cost than the contractor.
Option 4: all the above
Option 5: a and c


Which is a process used in Procurement Management to document product requirements and identify potential sources?


Option 1: Solicitation planning
Option 2: Procurement planning
Option 3: Source selection
Option 4: Contract administration
Option 5: Contract closeout


Which of the following are examples of indirect costs?


Option 1: Salaries of corporate executives
Option 2: Salaries of full-time project staff
Option 3: Overhead costs
Option 4: a and b
Option 5: a and c


Which is a tool or technique used in the schedule development process to calculate theoretical early and late start and finish dates for all project activities?


Option 1: Resource pool description
Option 2: Mathematical analysis
Option 3: Duration compression
Option 4: Activity duration estimates
Option 5: Analogous estimating


What is the BEST technique to ensure proper contract closure?


Option 1: Contract documentation
Option 2: Procurement audits
Option 3: Scope change control
Option 4: Formal acceptance
Option 5:


What does estimate at complete mean?


Option 1: Each anticipated cost for project
Option 2: Estimated average cost at project completion
Option 3: Anticipated total cost at project completion
Option 4: Anticipated expenses at project completion
Option 5:


Under what circumstances does contract close-out not involve product verification?


Option 1: When contract does not contain verification clause
Option 2: When stakeholder signs a product acceptance document
Option 3: When there is a material breech
Option 4: All of the above
Option 5:


Which is a process included in Project Risk Management:


Option 1: Risk identification
Option 2: Qualitative risk analysis
Option 3: Risk response planning
Option 4: Risk monitoring and response control
Option 5: All of the above


What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack?


Option 1: Lots of free float
Option 2: Idle resources
Option 3: Negative float
Option 4: Positive float
Option 5:


What do project planning documents help to establish?


Option 1: Project charter
Option 2: Framework for performance measurement
Option 3: Project budget
Option 4: Personnel pay scale
Option 5:


When the project team directs staff assignments, what is not considered in the selection of a staff


Option 1: Previous experience
Option 2: Staff age
Option 3: Availability
Option 4: Personal interest
Option 5: Personal characteristics


When is the earliest time administrative closure should be completed?


Option 1: At the end of each project phase
Option 2: At the end of the project
Option 3: Whenever a deliverable is complete
Option 4: Whenever a new project manager takes over a project
Option 5:


Which is a basis for a definition of the user's needs?


Option 1: Work breakdown structure
Option 2: Functional requirements
Option 3: Project cost estimate
Option 4: Selection of personnel
Option 5: Termination decision


If a project has an 80% chance of having the scope defined by a certain date and a 70% chance of obtaining approval for the scope by a certain date, what is the probability of both events occurring?


Option 1: 75%
Option 2: 65%
Option 3: 50%
Option 4: 56%
Option 5: 66%

Practice Free Total PMP Set 9 Questions online

By Practicing the below question set :
The student will get the basic and advanced knowledge on Total PMP Set 9.
The student will learned the priciples and methedology of Total PMP Set 9.
The student will evaluate the knowledge level on Total PMP Set 9.
Student can practice number of times the question till he is clear.
Student can provide the review / feedback / suggestion on the questions which will help to others.
The question contains the simple to complex level difficulties so that student can improve the knowledge.


Kindly Note : The information provided here is just indicative information and is provided on “as is” and “as available” basis . We make no claims on accuracy and reliability of the information. For correct/current information kindly contact concerned college/institution/authorities

Advertisements
Advertisements

Mail: Support@gicgac.com