Learn and Practice Free Total PMP Set 5 questions

Click below to Practice Free Total PMP Set 5 Questions


You can get answer of the below sample questions by going through the above Question sets.


From a buyer's standpoint, which of the following is true?


Option 1: Procurement planning should include consideration of potential subcontracts
Option 2: Procurement planning does not include consideration of potential subcontracts since this is the duty of the contractor.
Option 3: Subcontractors are first considered during the Solicitation Process
Option 4: none of the above
Option 5:


Frederick Herzberg identified all of the following are motivators of technical employees except


Option 1: peer recognition
Option 2: the supervisor's personality
Option 3: the work assignment
Option 4: the work responsibility
Option 5: the opportunity to learn new skills


Formal acceptance by the client or sponsor of the project should be preapred and distributed during which process?


Option 1: Information Distribution
Option 2: Administrative Closeout
Option 3: Organizational Planning
Option 4: Performance Reporting
Option 5:


In a weak matrix the project manager's authority is likely to be:


Option 1: Non-existent
Option 2: Low
Option 3: Limited
Option 4: Medium to high
Option 5: High


Ideally, communication between the project manager and the project team members should take place:


Option 1: Via daily status reports.
Option 2: Through approved documented forms.
Option 3: By written and oral communication.
Option 4: Through the formal chain of command.
Option 5:


During what Time Management Process are the specific activities that must be performed to produce the deliverables in the WBS identified and documented?


Option 1: Activity Sequencing
Option 2: Activity Definition
Option 3: Schedule Development
Option 4: Activity Duration Estimating
Option 5:


In a cost plus fixed fee contract, how can the fee change?


Option 1: It cannot change.
Option 2: It can change if change orders are issued.
Option 3: It can only be increased by 10% if there is an unexpected cost overrun.
Option 4: It can be decreased under certain circumstances.
Option 5:


In which stage of the negotiation meeting are points of concession identified?


Option 1: probing
Option 2: closure
Option 3: agreement
Option 4: scratch bargaining
Option 5:


Goals of interpersonal communications should include all EXCEPT


Option 1: producing action or change
Option 2: intimidation
Option 3: gaining acceptance for yourself and/or your ideas
Option 4: understanding the intent of others
Option 5: being understood by others


In order to anticipate your management's approval of the amount of risk you plan to take on with your chosen project approach, you would use


Option 1: Probability analysis
Option 2: The Delphi method
Option 3: The Monte Carlo method
Option 4: The utility theory
Option 5:


Dual reporting is most likely to occur in which type of organization?


Option 1: Functional
Option 2: Projectized
Option 3: Matrix
Option 4: Laissez-faire
Option 5: None of the above


For Christmas, you give your government client a leather brief case. You are in violation of the responsibility to:


Option 1: Comply with the law.
Option 2: Comply with regulations.
Option 3: Provide accurate information.
Option 4: Protect conflict of interest.
Option 5:


In an "activity-on arrow" network, the nodes represent _______ and may also be _______.


Option 1: A stopping point; transition points
Option 2: Zero time usage; milestones
Option 3: A use of one time unit; decision points
Option 4: Connector points for events; duplicates of other nodes
Option 5: Activities of importance; major consumers of time


Human resource administration is the primary responsibility of the:


Option 1: Project Management Team
Option 2: Human Resources Department
Option 3: Executive Manager
Option 4: Project Manager
Option 5: Line Managers


During the project scope planning process, the work breakdown structure should be developed to:


Option 1: The sub-project level.
Option 2: The level determined by the project office.
Option 3: A level allowing for adequate estimates.
Option 4: The cost center level.
Option 5:

Practice Free Total PMP Set 5 Questions online

By Practicing the below question set :
The student will get the basic and advanced knowledge on Total PMP Set 5.
The student will learned the priciples and methedology of Total PMP Set 5.
The student will evaluate the knowledge level on Total PMP Set 5.
Student can practice number of times the question till he is clear.
Student can provide the review / feedback / suggestion on the questions which will help to others.
The question contains the simple to complex level difficulties so that student can improve the knowledge.


Kindly Note : The information provided here is just indicative information and is provided on “as is” and “as available” basis . We make no claims on accuracy and reliability of the information. For correct/current information kindly contact concerned college/institution/authorities

Advertisements
Advertisements

Mail: Support@gicgac.com