Learn and Practice Free Time and Work Set 1 questions

Click below to Practice Free Time and Work Set 1 Questions


You can get answer of the below sample questions by going through the above Question sets.


Twelve men can complete a work in 8 days. Three days after they started the work, 3 more men joined. In how many days will all of them together complete the remaining work?


Option 1: 2
Option 2: 5
Option 3: 4
Option 4: 6
Option 5:


A can do a piece of work in 7 days of 9 hours each and B can do it in 6 days of 7 hours each. How long will they take to do it, working together 8*(2/5) hours a day?


Option 1: 3 days
Option 2: 5 days
Option 3: 4 days
Option 4: None of these
Option 5:


If 10 men or 18 boys can do a piece of work in 15 days, then 25 men and 15 boys together will do twice the work in:


Option 1: 4 and half days
Option 2: 8 days
Option 3: 9 days
Option 4: 36 days
Option 5:


A, B and C are employed to do a piece of work for Rs. 529. A and C are supposed to finish 19/23 of the work together. How much shall be paid to B ?


Option 1: Rs. 82
Option 2: Rs. 300
Option 3: Rs. 92
Option 4: Rs. 437
Option 5:


Ram can do a piece of work in 8 days which Shyam can finish in 12 days. If they work at it on alternate days with Ram beginning, in how many days, the work will be finished?


Option 1: 9 and 1/3
Option 2: 9 and 1/24
Option 3: 9 and 1/2
Option 4: 10 and 1/3
Option 5:


A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the remaining work in 42 days. The two together could complete the work in :


Option 1: 24 days
Option 2: 30 days
Option 3: 25 days
Option 4: 35 days
Option 5:


A is twice as good a workman as B and ‘together they complete a work in 15 days. In how many days can the work be completed by B alone.


Option 1: 22 * (1/2)
Option 2: 37 * (1/2)
Option 3: 30
Option 4: 45
Option 5:


45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work?


Option 1: 4
Option 2: 6
Option 3: 5
Option 4: 8
Option 5:


A and B together can do a piece of work in 12 days, which B and C together can do in 16 days. After A has been working at it for 5 days and B for 7 days, C finishes in 13 days. In how many days C alone will do the work?


Option 1: 16
Option 2: 36
Option 3: 24
Option 4: 48
Option 5:


A can do a piece of work in 30 days while B alone can do it in 40 days. In how many days can A and B working together do it?


Option 1: 17.14
Option 2: 42.75
Option 3: 27.14
Option 4: 70
Option 5:

Practice Free Time and Work Set 1 Questions online

By Practicing the below question set :
The student will get the basic and advanced knowledge on Time and Work Set 1.
The student will learned the priciples and methedology of Time and Work Set 1.
The student will evaluate the knowledge level on Time and Work Set 1.
Student can practice number of times the question till he is clear.
Student can provide the review / feedback / suggestion on the questions which will help to others.
The question contains the simple to complex level difficulties so that student can improve the knowledge.


Kindly Note : The information provided here is just indicative information and is provided on “as is” and “as available” basis . We make no claims on accuracy and reliability of the information. For correct/current information kindly contact concerned college/institution/authorities