Learn and Practice Free Scope Management Set 1 questions

Click below to Practice Free Scope Management Set 1 Questions


You can get answer of the below sample questions by going through the above Question sets.


The MAJOR processes for project integration management are:


Option 1: Project plan development, project plan execution, and overall change control.
Option 2: Project plan development, project plan execution, and scope change control.
Option 3: Project plan development, overall change control, and scope change control.
Option 4: Project plan development, initiation, and overall change control.
Option 5:


Project sponsors have the GREATEST influence on the scope, quality, time, and cost of the project during the:


Option 1: Concept phase.
Option 2: Development phase.
Option 3: Execution phase.
Option 4: Close-down phase.
Option 5:


Ideally, communication between the project manager and the project team members should take place:


Option 1: Via daily status reports.
Option 2: Through approved documented forms.
Option 3: By written and oral communication.
Option 4: Through the formal chain of command.
Option 5:


A project's payback period ends when:


Option 1: Profit maximum is realized.
Option 2: Unit profit is realized.
Option 3: Monthly revenue exceeds monthly costs.
Option 4: Cumulative revenue equals cumulative costs.
Option 5:


A scope statement is important because it:


Option 1: Provides the basis for making future project decisions.
Option 2: Provides a brief summary of the project.
Option 3: Approves the project for the stakeholders.
Option 4: Provides criteria for measuring project cost.
Option 5:


he following project management tools EXCEPT:


Option 1: Critical path analysis.
Option 2: Technical performance metrics.
Option 3: Risk mitigation plans.
Option 4: Forecasted final costs and schedule estimates.
Option 5:


During the project scope planning process, the work breakdown structure should be developed to:


Option 1: The sub-project level.
Option 2: The level determined by the project office.
Option 3: A level allowing for adequate estimates.
Option 4: The cost center level.
Option 5:


The decomposition process is a technique used to construct a:


Option 1: Precedence network.
Option 2: Critical Path Method Diagram.
Option 3: Variance analysis.
Option 4: Work breakdown structure.
Option 5:


IRST topic to address to the team in the kick-off meeting?


Option 1: Identify team roles and responsibilities.
Option 2: Review detailed schedule.
Option 3: Discuss cost estimates.
Option 4: Emphasize your authority.
Option 5:


Constructive team roles include:


Option 1: Encourager, initiator, and gatekeeper.
Option 2: Information giver, devils advocate, and clarifier.
Option 3: Withdrawer, harmonizer, and blocker.
Option 4: Summarizer, recognition seeker, and information seeker.
Option 5:


A project schedule completion date will change if:


Option 1: The critical path is reduced.
Option 2: The contingency is no longer available.
Option 3: No float time is available.
Option 4: Project resources are reduced.
Option 5:


he conflict, to get the project back on schedule, you should consider:


Option 1: Crashing the schedule.
Option 2: Performing resource leveling.
Option 3: Conducting reverse resource allocation scheduling.
Option 4: Utilizing the critical chair resources.
Option 5:


Risk quantification includes:


Option 1: Enumerating sources of internal and external events.
Option 2: Identifying potential events and impact.
Option 3: Evaluating probability and impact.
Option 4: Developing contingency plans and resources.
Option 5:


In which project phase do you have the GREATEST influence on project risk?


Option 1: Conceptual
Option 2: Design
Option 3: Execution
Option 4: Implementation
Option 5:


A precise description of a deliverable is called a:


Option 1: Specification.
Option 2: Baseline.
Option 3: Work package.
Option 4: Work breakdown structure element.
Option 5:

Practice Free Scope Management Set 1 Questions online

By Practicing the below question set :
The student will get the basic and advanced knowledge on Scope Management Set 1.
The student will learned the priciples and methedology of Scope Management Set 1.
The student will evaluate the knowledge level on Scope Management Set 1.
Student can practice number of times the question till he is clear.
Student can provide the review / feedback / suggestion on the questions which will help to others.
The question contains the simple to complex level difficulties so that student can improve the knowledge.


Kindly Note : The information provided here is just indicative information and is provided on “as is” and “as available” basis . We make no claims on accuracy and reliability of the information. For correct/current information kindly contact concerned college/institution/authorities

Advertisements
Advertisements

Mail: Support@gicgac.com