Learn and Practice Free Risk Management Set 1 questions

Click below to Practice Free Risk Management Set 1 Questions


You can get answer of the below sample questions by going through the above Question sets.


Which of the following are outputs of the Scope Change Control Process?


Option 1: Scope changes
Option 2: Corrective action
Option 3: Lessons learned
Option 4: All of the above
Option 5: None of the above


You are finding it difficult to evaluate the exact cost impact of risks. You should evaluate on a:


Option 1: Quantitative basis
Option 2: Numerical basis
Option 3: Qualitative basis
Option 4: Economic basis
Option 5:


Using a contractor to perform a high-risk task is which form of risk response?


Option 1: Insurance
Option 2: Assumption
Option 3: Alternative
Option 4: Transference
Option 5: Mediation


Problem solving addresses only the causes of problems on the project.


Option 1: True
Option 2: False
Option 3:
Option 4:
Option 5:


A process that is not part of Project Risk Management is:


Option 1: Identification
Option 2: Solicitation
Option 3: Qualitative and Quantitative Analysis
Option 4: Response Development
Option 5: Monitoring and Control


For Christmas, you give your government client a leather brief case. You are in violation of the responsibility to:


Option 1: Comply with the law.
Option 2: Comply with regulations.
Option 3: Provide accurate information.
Option 4: Protect conflict of interest.
Option 5:


Which is a process included in Project Risk Management:


Option 1: Risk identification
Option 2: Qualitative risk analysis
Option 3: Risk response planning
Option 4: Risk monitoring and response control
Option 5: All of the above


Inputs to Quantitative Risk Analysis do not include:


Option 1: Stakeholder risk tolerance
Option 2: Identified risks
Option 3: List of prioritized risks
Option 4: Historical information
Option 5: Expert judgment


Tools and techniques used in Quantitative Risk analysis include:


Option 1: Interviewing
Option 2: Sensitivity analysis
Option 3: Decision tree analysis
Option 4: Simulation
Option 5: All of the above


Outputs to Risk Response Planning do not include:


Option 1: Residual risks
Option 2: Contingency reserve amounts
Option 3: Contractual agreements
Option 4: Risk response plan
Option 5: Corrective action plan


Simulations typically use what kind of technique to analyze the behavior or performance of a system?


Option 1: Expected monetary value
Option 2: Decision trees
Option 3: Monte Carlo
Option 4: Statistical sums
Option 5: Expert judgment


What document outlines the action steps to be taken if an identified risk event should occur:


Option 1: Risk response plan
Option 2: Project plan
Option 3: Corrective action plan
Option 4: Contingency plan
Option 5: All of the above


Which of the following statements is in agreement with McGregor's concepts concerning Theory X and Theory Y managers?


Option 1: Theory X managers view subordinates as being lazy, irresponsible, and resistant to change
Option 2: Theory Y managers view subordinates as being imaginative, creative, and willing to accept responsibility
Option 3: Theory X managers tend to be autocratic whereas Theory Y managers are more likely to delegate responsibility
Option 4: a and b
Option 5: All of the above


The independence of two events in which the occurrence of one is not related to the occurrence of the other is called:


Option 1: event phenomenom
Option 2: independent probability
Option 3: statistical independence
Option 4: statistical probability
Option 5:


The highest risk impact generally occurs during which of the following project life cycle phases?


Option 1: Concept and planning
Option 2: Concept and implementation
Option 3: Planning and implementation
Option 4: Implementation and closeout
Option 5: Concept and closeout

Practice Free Risk Management Set 1 Questions online

By Practicing the below question set :
The student will get the basic and advanced knowledge on Risk Management Set 1.
The student will learned the priciples and methedology of Risk Management Set 1.
The student will evaluate the knowledge level on Risk Management Set 1.
Student can practice number of times the question till he is clear.
Student can provide the review / feedback / suggestion on the questions which will help to others.
The question contains the simple to complex level difficulties so that student can improve the knowledge.


Kindly Note : The information provided here is just indicative information and is provided on “as is” and “as available” basis . We make no claims on accuracy and reliability of the information. For correct/current information kindly contact concerned college/institution/authorities

Advertisements
Advertisements

Mail: Support@gicgac.com