Learn and Practice Free Chain Rule Set 3 questions
Click below to Practice Free Chain Rule Set 3 Questions
You can get answer of the below sample questions by going through the above Question sets.
39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, working 6 hours a day, complete the work?
Option 1: 10
Option 2: 13
Option 3: 14
Option 4: 15
Option 5:
A fort had provision of food for 150 men for 45 days. After 10 days, 25 men left the fort. The number of days for which the remaining food will last, is:
Option 1: 29
Option 2: 37
Option 3: 42
Option 4: 54
Option 5:
36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work ?
Option 1: 24 days
Option 2: 35 days
Option 3: 28 days
Option 4: 27 days
Option 5:
Some persons can do apiece of work in 12 days. Two times the number of such persons will do half of that work in
Option 1: 6 Days
Option 2: 12 Days
Option 3: 4 Days
Option 4: 3 Days
Option 5:
10 men, working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the work in 12 days ?
Option 1: 4 hours a day
Option 2: 5 hours a day
Option 3: 6 hours a day
Option 4: 7 hours a day
Option 5:
If 18 bindres bind 900 books in 10 days , How many binders will be required to bind 660 books in 12 days?
Option 1: 22
Option 2: 14
Option 3: 13
Option 4: 11
Option 5:
If a quarter Kg of potato costs 60 paise, How many paise will 200 gm cost?
Option 1: 48 Paise
Option 2: 54 Paise
Option 3: 56 Paise
Option 4: 72 Paise
Option 5:
Running at the same constant rate, 6 identical machines can produce a total of 270 bottles per minute. At this rate, how many bottles could 10 such machines produce in 4 minutes?
Option 1: 648
Option 2: 1800
Option 3: 2700
Option 4: 1080
Option 5:
If 16 men working 7 hours day can plough a fieid in 4l days, inhow many days will 14 men working 12 hours a clay plough the samefield ?
Option 1: 46
Option 2: 32
Option 3: 35
Option 4: 30
Option 5:
An industrial loom weaves 0.128 metres of cloth every second. Approximately, how many seconds will it take for the loom to weave 25 metre of cloth ?
Option 1: 194 seconds
Option 2: 195 seconds
Option 3: 196 seconds
Option 4: 197seconds
Option 5:
Practice Free Chain Rule Set 3 Questions online
By Practicing the below question set :
The student will get the basic and advanced knowledge on Chain Rule Set 3.
The student will learned the priciples and methedology of Chain Rule Set 3.
The student will evaluate the knowledge level on Chain Rule Set 3.
Student can practice number of times the question till he is clear.
Student can provide the review / feedback / suggestion on the questions which will help to others.
The question contains the simple to complex level difficulties so that student can improve the knowledge.
Kindly
Note : The information provided here is just indicative
information and is provided on “as is”
and “as available” basis . We make no
claims on accuracy and reliability of the information.
For correct/current information kindly contact concerned
college/institution/authorities